 CONSTRUCTION TO BEGIN IN OCTOBER 2017

 

The reconstruction of Peters Creek Parkway road and interchange is slated to start on October 23 and continue through Fall 2018. This phase of construction is referred to as Segment A. You will start to see heavy equipment roll in as work begins. There will be temporary lane closures on both Peters Creek Parkway and Business 40 during this time frame, as presented below. Remember that the full closure of Business 40 will only occur AFTER completion of Segment A in Fall 2018.

Here’s what YOU can expect beginning in October:

ON PETERS CREEK PARKWAY:

  • Work crews will begin site preparations on October 23. While two lanes of traffic in each direction will be maintained on Peters Creek Parkway during most of construction (click here to see a graphic of how traffic will flow), there will be some initial temporary, nighttime (9PM - 6AM) and non-peak, daytime (9AM – 4PM) lane closures on Peters Creek Parkway.
  • Detour signs will be placed on local streets, similar to what you already see if a road is closed.

ON BUSINESS 40 UNDER PETERS CREEK PARKWAY BRIDGE:

  • Starting October 23 through early December, NCDOT will close the inner eastbound and westbound lanes of Business 40, as shown here. These lane closures will occur overnight from 9:00 p.m. to 6:00 a.m.
  • Starting October 25 between midnight and 6:00 a.m., in addition to the above, eastbound traffic will be diverted up the exit ramp at Peters Creek Parkway, over Peters Creek Parkway, and down the Business 40 on-ramp from Peters Creek Parkway (click here to see an image).
  • While the distance of the lane closures will be short, there will likely be traffic delays as two lanes merge into one in each direction. Please consider taking another route if possible, to avoid delays.
  • Message boards will be placed on Business 40 to advise drivers of lane closures. Ample notice of lane closures and detours via news and social media will also be provided so that travelers can prepare.

4TH STREET BRIDGE:

  • Also during this time, the 4th Street Bridge will be closed to traffic while it is being replaced. The bridge will re-open once complete.

APPLE AND GREGORY STREETS:

  • Will close on October 9.

CURRENT PREPARATION WORK

  • Installation of new water line on 1st Street between Church Street and Peters Creek Parkway.
  • Work on the water line will be constructed in "two block" segments, as shown here.
  • Work began on Church Street and will continue to progress westward until the project is completed at Peters Creek Parkway.
  • For more information, call CityLink311.
ATTENTION: For your benefit and understanding, a complete presentation of the project can be viewed in two formats, as listed below. The presentation is dynamic and ever-changing as the construction work may vary due to unforeseen obstacles and/or weather. However, the overall improvements and construction segments are constant and correct. The text below is current and correct:

Click here to view the presentation in PowerPoint, complete with script.

Click here to view the presentation in video format.
​​
 
-    -    -    -    -    -    -    -    -    -    -    -    -    -    -    -    -    -    -    -    -    -    -    -    -    -    -    -    -    -    -    -    -    -    
​​​
​​​​​